Accessible Routes
BFID: 187711
There are multiple issues with this curb ramp including:
The curb ramp has a running slope up to 11.9%.
There is not a level landing as the ramp extends most of the width of the sidewalk, creating severe cross slope issues.
Side flares are up to 35%.
There is 1/2" vertical displacement between the curb and curb ramp ramp, and between the gutter and the asphalt paving.
Citation:
2010 ADAS Section 406
Curb Ramps
As Built:
There are multiple issues with this curb ramp at the access aisle.
Recommendation:
Remove and replace with a parallel curb ramp.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187710
There are 4 concrete panels with running and cross slope up to 9.7%. One also has a divot measuring 3"x1.5"x3/4" deep.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
There are multiple issues with this section of sidewalk.
Recommendation:
Remove and replace panels to provide maximum 2% cross slope in all directions.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190037
The accessible path of travel contains cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
This section of sidewalk has 6 sections of sidewalk between 3.4-5% cross slope and two others in a turn area between 3.3-4.8% cross slope. There is also a 1.25" gap that is 1" deep.
Recommendation:
Replace walk surface to at or under 2%.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190038
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
This section of sidewalk has 6 sections of sidewalk between 2.6-4.5% cross slope 5.1-7.9% running slope. Also there is an area of 3/4" vertical displacement and the base of this ramp has a 3.7% turn area (no level landing).
Recommendation:
Grade at under 5% if feasible and fix all cross slopes. We may need to install ramp provisions here if we can't lower grade to under 5%.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187726
There are three fractured panels with up to 1" vertical displacement.
The cross slope is between 2.8% and 3.3%.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
There are multiple issues with this section of sidewalk.
Recommendation:
Remove and replace the three panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187725
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope for 7 panels is between 3% and 4.4%.
Recommendation:
Remove and replace the 7 panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187724
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope for three panels is between 3.5% and 4.4% at a turn area.
Recommendation:
Remove and replace the panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187723
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope of three panels is up to 4.2%.
Recommendation:
Remove and replace the three panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187722
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope of 13 panels is between 2.5% and 4%.
Recommendation:
Remove and replace the panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187721
There are multiple issues with this curb ramp including:
The ramp creates an 8.9% cross slope in the sidewalk and it exceeds max curb ramp running slope.
The landing has a running slope of 3.7%.
There is not a receiving or connecting ramp on the other side of Memorial Dr. which creates the impression this is a drop off area or it is an orphan ramp. This is not a safe drop off area.
Citation:
2010 ADAS Section 406
Curb Ramps
As Built:
There are multiple issues with this curb ramp southeast of the Veterans Memorial.
Recommendation:
This curb ramp is not needed. Remove it and replace with sidewalk
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190042
Following the turn there is a 1-1/2" gap between panels that is 3/4" deep. We also have 12 panels with between 2.5-5.1% cross slope.
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The sidewalk east of the Veterans memorial has 12 panels with cross slope issues.
Recommendation:
Remove and replace the panels at the turning points and at least the three panels with high cross slopes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187720
At the first turn from the Peace Officers Memorial, the cross slope is up to 10%. Then we have 3 full size pads with 9.8, 12.8 and 13.7% cross slope respectively. At the second turn, the cross slope is up to 11.4%.
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The sidewalk southeast of the Veterans memorial has serious running and cross slope issues.
Recommendation:
Remove and replace the panels at the turning points and at least the three panels with high cross slopes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190039
The accessible path of travel contains cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
This section of sidewalk has 4 sections of sidewalk prior to curb ramp between 4.8-7.7% cross slope. Then, as mentioned in finding #5, there is 11.6% cross slope on ramp face.
Recommendation:
Replace all pads.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187712
The cross slope of the pedestrian access route is excessive. All pads need to be replaced from the curb ramp to the next turn area.
The cross slope of pedestrian access routes shall be 2 percent maximum.
Citation:
2011 PROWAG Section R302.6
Except as provided in R302.6.1 and R302.6.2 (Pedestrian Street Crossings Without Yield or Stop Control and Midblock Pedestrian Street Crossings), the cross slope of pedestrian access routes shall be 2 percent maximum.
Advisory R302.6 Cross Slope. The cross slope requirements in R302.6 apply to sidewalks and other pedestrian circulation paths, pedestrian street crossings and at-grade rail crossings, and pedestrian overpasses and underpasses and similar structures (see R302.2). The cross slope of the pedestrian access route is measured perpendicular to the direction of pedestrian travel. Cross slope requirements are contained in R304.5.3 for curb ramps and blended transitions, and in R407.3 for ramps.
As Built:
From the curb ramp we have 13 pads with a cross slope between between 3-4.3% cross slope.
Recommendation:
Remove and replace all pads to a maximum of 2% cross slope from the curb ramp to the next turn area.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190040
The cross slope of the pedestrian access route is excessive. All pads need to be replaced from the curb ramp to the next turn area.
The cross slope of pedestrian access routes shall be 2 percent maximum.
Citation:
2011 PROWAG Section R302.6
Except as provided in R302.6.1 and R302.6.2 (Pedestrian Street Crossings Without Yield or Stop Control and Midblock Pedestrian Street Crossings), the cross slope of pedestrian access routes shall be 2 percent maximum.
Advisory R302.6 Cross Slope. The cross slope requirements in R302.6 apply to sidewalks and other pedestrian circulation paths, pedestrian street crossings and at-grade rail crossings, and pedestrian overpasses and underpasses and similar structures (see R302.2). The cross slope of the pedestrian access route is measured perpendicular to the direction of pedestrian travel. Cross slope requirements are contained in R304.5.3 for curb ramps and blended transitions, and in R407.3 for ramps.
As Built:
We have 3 pads in a turn point with 4.6% and 4.8% cross slope.
Recommendation:
Remove and replace all pads to a maximum of 2% cross slope in the turn area.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187713
The accessible path of travel contains cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are 35 panels from the turning point to the next turning area with cross slopes between 2.5% and 4.6%.
Recommendation:
Remove and replace all the panels along this route.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190041
The accessible path of travel contains cross slopes greater than 2%.
Surface cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope). When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The turning point has low to mid 3% cross slopes and fracturing with up to 1" vertical displacement. There is also a 1-1/2" gap between panels.
Recommendation:
Remove and replace all the panels along this route.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187714
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp. Surface cross slopes must not exceed one unit vertical in 48 units. Horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are 16 panels with running slopes between 5.4% and 8.1%. Along this route are also 2 pads with cross slopes of 2.8 and 3%.
Recommendation:
Since this leads to a very inaccessible route (very steep ramp) we should just fix the the 2 pads with cross slope issues.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187716
The surface of the pedestrian access route has openings greater than 1/2 inch.
Citation:
2011 PROWAG Section R302.7.3
Horizontal openings in gratings and joints shall not permit passage of a sphere more than 13 mm (0.5 in) in diameter. Elongated openings in gratings shall be placed so that the long dimension is perpendicular to the dominant direction of travel.
As Built:
There is a 3/4" gap in the sidewalk.
Recommendation:
Remove and replace the panel.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190044
The accessible route of travel on the walk or sidewalk contains cross slopes greater than 2%.
Cross slopes shall not exceed one unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The new curved sidewalk on which the Submariner, Marines and Buffalo Solders memorials are accessed has 18 sidewalk panels with cross slopes between 3.9 and 9.5%.
Recommendation:
Replace all panels to 2% cross slope.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187717
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The Submariner monument has 2 panels out of compliance with cross slope up to 7.5% and running slope up to 9.6%.
Recommendation:
Remove and replace the panels to provide maximum 2% cross slope and maximum 5% running slope. The running slope can be up to 8.33% if handrails are provided on both sides of the sidewalk.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187718
There are two panels with running slope up to 8.8 and 9.5%. One panel has a cross slope up to 4.2%.
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The Marine Semper Fi monument there are several panels out of compliance.
Recommendation:
Remove and replace at least the five panels. See Notes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187719
There are three panels with running slopes between 6-9%. The sidewalk has a cross slope of 9.1% where it abuts the memorial concrete. There are also grooves in the pavement creating over 1/2" displacement in the pavement surface. Also there is a memorial bench not on an accessible route. The bench doesn't necessarily need to meet any standards but it has inscriptions on it which may be of value.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
The path of travel to the Buffalo Soldiers Monument is not accessible.
Recommendation:
Remove and replace the three panels. Determine if bench is decorative or has important historical or other information which may necessitate moving it.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187729
There are four panels leading to a turning point with running slope between 5.8% and 6.8%, with no ramp provisions.
The intersection has two panels with slopes up to 5.9%.
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The running and cross slopes exceed allowable values.
Recommendation:
Remove and replace to provide maximum 5% running slope, maximum 2% cross slope, and maximum 2% in all directions at the turning point or put in proper ramp or mark and create a designated accessible route leading into the memorial from the parking area. This is the best choice as it is the closest.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187730
Sidewalk cross slopes exceed allowable values.
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope of eleven panels near the Forward Air Controllers Monument is between 3.8% and 7.5%.
Recommendation:
Fix cross slopes beween connecting routes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190043
Sidewalk cross slopes exceed allowable values the high slopes can be either running or cross slopes depending on direction of travel.
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The Forward Air Controllers Monument has slopes of between 4-6%.
Recommendation:
Explore fixing slopes in this area particularly at the entry.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187731
The accessible path of travel contains cross slopes greater than 2%. See notes.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The cross slope of 3 panels is between 3% and 3.3%.
Recommendation:
Remove and replace the panels.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187732
There are multiple panels with cross slopes up to 6.6%. The turning point panel to the monument has cross slope/running slope up to 4.4%.
The accessible path of travel contains cross slopes greater than 2%.
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are multiple cross slope issues with the sidewalk near the Air Force Controllers Monument.
Recommendation:
Remove and replace to provide maximum 2% cross slope and maximum 2% in all directions at the turning point. This will possible be the entire route between perpendicular paths.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187733
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are 3 panels with running slope between 5.5% and 9.5%.
Recommendation:
Remove and replace to provide maximum 5% running slope, or install handrails on both sides if the sidewalk is up to 8.33% running slope.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187735
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There are four panels with running slope between 5.4% and 7.7%.
Recommendation:
Remove and replace panels to provide maximum 5% running slope or install handrails on both sides of the sidewalk if the running slope exceeds 5%.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187734
There are multiple areas with fractures and gaps. There are 20 panels with cross slopes between 3% and 5.2% along the outer walking area. There are four other levels with 6" steps to access each nigher level. See notes.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
There are multiple issues with the sidewalk loop around the bell tower.
Recommendation:
Remove and replace the panels to provide maximum 2% cross slope. Replace the fractured panels and fill gaps.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187736
The running slope of the sidewalk is between 7.2% and 8.1%.
The cross slope is 3% to 4.5% for two panels.
There are areas with up to 1" vertical displacement behind the memorial.
The maximum allowed running slope is 5%, or up to 8.33% if handrails are provided. The maximum cross slope allowed is 2%.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
There are multiple issues with the sidewalk to and around the 89th Infantry Division Monument.
Recommendation:
Remove and replace the panels with high cross and running slopes.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187737
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The running slope of two panels to the Purple Heart monument is up to 5.6%. We also have a 4.5% cross slope at the Purple Heart memorial.
Recommendation:
Remove and replace to provide maximum 5% running slope and 2% cross slope.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187738
The route of travel at this location does not provide the required minimum width.
The minimum clear width for sidewalks and walks is 36 inches.
Citation:
2010 ADAS Section 403.5.1
Except as provided in 403.5.2 and 403.5.3, the clear width of walking surfaces shall be 36 inches (915 mm) minimum.
2010 ADAS Section 403.5.1 Exception
The clear width shall be permitted to be reduced to 32 inches (815 mm) minimum for a length of 24 inches (610 mm) maximum provided that reduced width segments are separated by segments that are 48 inches (1220 mm) long minimum and 36 inches (915 mm) wide minimum.
As Built:
The sidewalk to the Canadian's Monument reduces in width from 48" to 24".
Recommendation:
Replace the sidewalk with a 5'-0" wide sidewalk.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187739
There is no accessible route to the Aerospace Monument.
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
Citation:
2015 IBC Section 1104.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements and accessible spaces that are on the same site.
2010 ADAS Section 206.2.2
At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site.
As Built:
The sidewalk to the Aerospace Monument reduces in width from 46" to 24". It also has up to a 3.6% cross slope and a running slope between 9-16%.
Recommendation:
Replace entire route to 2% or less cross slope and a running slope under 5%. Also, the route must be at least 36" wide with a 60" wide turn around space at the bottom.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187740
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The running slope of these four panels is between 7.3% and 8.4%.
Recommendation:
Remove and replace the sidewalk to provide maximum 5% running slope, or maximum 8.33% with handrails on both sides.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 187741
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The sidewalk to the Sailors monument has 4 panels with running slope between 6.6% and 12% with up to a 2.8% cross slope.
Recommendation:
Remove and replace to provide maximum 5% running slope or up to 8.33% running slope with handrails on each side.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187742
In front of the monument the running slope is 5.1%. Around the monument, the running slope ranges from 4% to 5.2%.
The accessible route on the site contains running slopes greater than 5% and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
The running slope to and around the World War II monument exceed allowable values.
Recommendation:
Remove and replace the sidewalk to and around the monument.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 187743
The surface of the pedestrian access route has vertical discontinuities greater than 1/2 inch or between 1/4 inch and 1/2 inch that are not beveled.
Citation:
2011 PROWAG Section R302.7.2
Vertical surface discontinuities shall be 13 mm (0.5 in) maximum. Vertical surface discontinuities between 6.4 mm (0.25 in) and 13 mm (0.5 in) shall be beveled with a slope not steeper than 50 percent. The bevel shall be applied across the entire vertical surface discontinuity.Advisory R302.7.2 Vertical Surface Discontinuities. The allowance for vertical surface discontinuities is for occasional expansion joints and objects such as utility covers, vault frames, and gratings that cannot be located in another portion of the sidewalk outside the pedestrian access route. However, objects such as utility covers, vault frames, and gratings should not be located on curb ramp runs, blended transitions, turning spaces, or gutter areas within the pedestrian access route. This may not always be possible in alterations, but should be avoided wherever possible. Vertical surface discontinuities between unit pavers should be minimized.
As Built:
There is vertical displacement between 1/2" and 3/4".
Recommendation:
Grind to less than 1/2".
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
BFID: 190045
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There is a 6.3-7.3 running slope to the memorial with a cross slope in the sidewalk that is 3.4%.
Recommendation:
Fix cross slopes in the sidewalk leading to the memorial and determine distance on informational signs to get approach distance.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation
Additional Finding Photos
BFID: 190046
The accessible route contains running slopes greater than 5 percent and cross slopes greater than 2 percent across the width of the walk and has not been constructed as a ramp (i.e. handrails, wheel guides, etc.).
When the slope in the direction of travel of any walk exceeds 1 unit vertical in 20 units horizontal (5-percent slope), it must be constructed as ramp. Surface cross slopes must not exceed 1 unit vertical in 48 units horizontal (2-percent slope).
Citation:
2010 ADAS Section 403.3
The running slope of walking surfaces shall not be steeper than 1:20. The cross slope of walking surfaces shall not be steeper than 1:48.
As Built:
There is an up to 6.2% running slope to the memorial with a cross slope in the sidewalk that is 4.6%.
Recommendation:
Replace the pads to under 2% cross slope and under 5% running slope.
Barrier Priority:
High (1): Should be completed immediately. (Includes findings that have little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat)
Department:
Parks & Recreation