Main content
In Progress

Contact the project team and sign up for project updates via email: LasVegasRoyerProject@gmail.com

Project Infoline: 719-225-7389

Department:
Public Works
Phase 1 (Fall 2025)
  • Las Vegas Street will have one lane open with daytime flagging operations.
  • Temporary pavement and support structures will be constructed.
Phase 2 (Fall 2025 to Winter 2026)
  • Two-way traffic will move onto the temporary pavement.
  • Las Vegas Street will be raised and new pavement will be constructed.
Phase 3 (Spring 2026)
  • Two-way traffic will move onto the finished road on Las Vegas Street.
  • Twin Bridges Road will be constructed in this phase.
Phase 4 (Summer 2026)
  • In late summer or fall, the intersection of East Las Vegas Street and Royer Street will close for two weeks for concrete installation on the Royer Street railroad crossing.
  • Twin Bridges Road and the new railroad crossing will open.
  • The old crossing at Royer Street will be closed after Twin Bridges Road is open.
  • Royer Street will be converted to a cul-de-sac north of the railroad.
Phase 5 (Fall 2026)
  • Project Completion

Current Traffic Impacts:

Fall 2025 Road Closures and Detours
The Las Vegas Royer Railroad Relocation project is now in Phase 2. Traffic has been shifted to temporary pavement while crews raise East Las Vegas Street to connect with the future Twin Bridges Road. Currently, both lanes will stay open on the temporary pavement.


The Las Vegas/Royer Railroad Crossing Relocation Project involves construction of a new railroad crossing and roadway to replace the existing Royer Street railroad crossing. 

  • A new street, Twin Bridges Road, will be built under US Highway 24, connecting Las Vegas Street to the Hancock Expressway.
  • Upon completion, the existing Royer Street railroad crossing will be removed and a cul-de-sac will be constructed north of the railroad.