Main content
In Progress
Department:
City Engineering
March 24, 2025
  • Start reconstruction Block 1 (Colorado Avenue to Pikes Peak Avenue)
Early July 2025
  • Complete Block 1; start Block 2 (Pikes Peak Avenue to Kiowa Street)
September 2025
  • Complete Block 2; start reconstruction of Historic Busy Corner
Late 2025
  • Final pavement overlay for Tejon Street
Upload File
A cross section of Tejon Street that shows the new parking orientation and right of ways.

 

April 9, 2025 Update

Workers begin smoothing the concrete expansion of the Tejon St. sidewalk

Construction of the Tejon Street Revitalization Project – to enhance outdoor dining space, sidewalk accessibility and public safety -- is well underway between Colorado Avenue and Pikes Peak Avenue.  Work began March 24 with demolition and replacement of the sidewalk in front of the Unites States Olympic and Paralympic Committee headquarters at the northeast corner of Tejon Street and Colorado Avenue.

Similar removal and expansion of dining space and sidewalk continues northward in front of Red Gravy, Jack Quinn’s and Chipotle/Hibbard Building. Pedestrians are skillfully traversing between the temporary walkways and the newly installed sidewalks. 

The project team plans to cross the western outlet of AdAmAn Alley by late April and begin removal of patio railings and sidewalks, with replacement of the concrete surface to follow shortly after.  Work is expected to cross to the western side of Tejon in early May, depending on weather and other factors.

Traffic Impacts

For access and safety, these conditions continue until further notice:

  • Closure of northbound Tejon Street on Block 1 (Colorado Avenue to Pikes Peak Avenue)
  • Closure of street parking in Block 1 (Parking is $1/hour at our 3 city garages)
  • Note that Block 2 (Pikes Peak Avenue to Kiowa Street) should retain its parking spaces and
    north-south traffic until further notice.
  • Closures of lefthand and righthand turns from Colorado onto Tejon
  • Preservation of southbound Tejon
  • The ZEB route will continue with a northbound detour, and the northbound stop on Tejon will be moved south of Colorado Avenue in front of Plaza of the Rockies during work on Block 1.