Text DUBLIN to 866-762-3640 to receive text alerts regarding construction updates and traffic impacts.

Department:
Public Works
Public Works Department
Fall 2024 - Spring 2025

Complete final design and prepare construction documents

Early 2025

Start private utility relocations

Spring 2025 - Fall 2026

Construct storm sewer and surface improvements

Traffic Impacts

  • Dublin Boulevard will be closed to all traffic from just east of Fieler Drive to Mustang Rim Drive beginning Tuesday, May 27 through Friday, August 1. More information is available under the May 14, 2025 Construction Update.
  • During the weeks of May 11 and 18, Dublin Boulevard will have periodic right lane closures on weekdays from 8:30 a.m. to 3:00 p.m. Extended lane closures may occur on Saturdays. The closures will extend from Black Forest Road / Shimmering Creek Drive to Peterson Road.
  • The Sand Creek Trail will be closed in the area near and underneath Dublin Boulevard from May 19 to early August. A trail detour will be signed. Trail users will be directed to use sidewalks and signalized intersections to cross Dublin Boulevard.
  • Travelers should expect equipment and workers adjacent to the road.
  • The posted work zone speed limit may be reduced to 35 mph.
  • Follow signs and flagger directions when present.
  • View the Construction Updates tab for more information on construction and traffic impacts.